Extensive excavations for the concrete footings and foundations of the new Patient Care Tower are well underway. Over 1,000 metres of concrete have…
Extensive excavations for the concrete footings and foundations of the new Patient Care Tower are well underway. Over 1,000 metres of concrete have…
Bulk excavation for the new Vernon Jubilee Hospital Patient Care Tower is now complete. Work has begun on installing reinforcing concrete to the…
Bulk excavation is well underway and will be complete by the end of February. In order to keep down the amount of mud…
The demolition of the Alexander Wing is all but complete. There is ongoing utility work, which includes everything from underground water and sewer…
The demolition of the Alexander Wing is underway and should be complete by the end of January. Once the old building is removed,…